Build Diary

19th August 2004

Make first enquiry with Southern Helicopters

24th August

Take first ‘Helicopter Experience’ flight

31st August

Visit Southern Helicopters and pay deposit

9th September

Kit Stage 1 and 2 Delivered

21st September

Begin flight training at Rochester Airport

29th September

. Frame Powder Coated

28th October

First visit from CAA Regional Inspector

23rd November

Kit Stage 3 and 4 delivered

23rd November

First engineers inspection by Southern Helicopters

1st December

Receive written OK from Rotorway on proposed body screw changes

3rd December

Website launched

31st December

Clocked up 314 build hours so far.

15th January 2005

Passed my Air Law Examination  - Yippee.

24th January

Received my Medical Certificate - Fit and Healthy

4th February

Fitted engine

9th February

CAA inspection. Happy Bunnies so far.

2nd March

Receive OK from Rotorway on Cyclic Bearings Mod and Cabin Comfort ‘T’ piece mods.

19th March

Pass verbal safety test and take FIRST SOLO FLIGHT yippee

7th April

First Solo Circuit

18th May

Passed Human Performace Examination

24th May

Clocked up 661 build hours so far.

1st June

Passed RT Examination

3rd June

2nd engineers inspection

12th June

Passed Aural Comms Test

17th July

Had my first (and hopefully last) Major Moment. Ship and me unscathed

23rd July

Back in the saddle. Scared but OK.

4th August

Fly R22 into Redlands under my control for the first time.

8th August

9.30 PM  Fire up Exec engine. Perfect 1st time - so far. 940 hours into the build

3rd September

1st CAA Engineers Inspection

18th Sept

1st Tethered run up with blades on.

26th September

Clocked up 1068 build hours so far.

5th October

Passed Helicopter Technical Exam

7th October

Passed Helicopter Performance Exam

13th October

Passed Meteorology Exam - a Toughie!

26th October

Passed Navigation Exam - That’s the lot!!

16th November

First Solo Cross Country

23rd November

Completed final graphics details. The basic construction of my ship is finished. 1139 Hours total build time not including lying awake at nights, surfing the net for information, compiling this website and my own worksheets, talking and discussing things with other builders and the innumerable hours spent daydreaming and pondering things through.

Of course, the work never really ends but from now on it’s just tweeking and miaintenance.

18th December

1st Land Away Cross Country

20th January 2006

G-CDBK collected on a trailer by Southern Helicopters and taken to their base for final inspections and flight testing. (see pic below)

30th January

Completed Solo Cross-country qualifier. Rochester-Lydd-Goodwood-Rochester

 

Here’s progress on 20th February 2005. Exhaust, radiator and Oil bath fitted.

Here’s progress at 24th June. All panels finally trimmed and secured with fixings. Doors complete and removed for paint. Next step - all panels off for paint then wiring and instruments.

Here’s progress at 4th September 2005 - almost one year from delivery. The first Engineers Inspection was yesterday. Blades have been on and off. Engine’s running and all is sweet.

1st October 2005 Painted and assembled. Just waiting for insurance, graphics and Pilots license.

November 25th 2005. Ship’s finshed - it’s just down to me now.

Bye bye, for now.

 

[Home] [Specifications] [Frame] [Tub Split] [Body Assembly] [Roof Panel Modifications] [More Body Mods] [Interior Finishing] [Painting] [Screen] [Doors] [Skid Pants] [Controls] [Tail Boom & Fins] [Tail Rotor & Drive] [Chain Oil Bath] [Drive Train] [Rigging] [Cooling] [Instruments & Wiring] [Cabin Comfort] [Exhaust] [Silencer] [Heat Shield] [Fuel Tanks] [IT LIVES!! &Teething Troubles] [Testing] [Main Rotor Blades] [Miscellaneous] [Tools] [Parts Supply] [Build Diary] [Events] [Flight Training] [Links] [Toys and Dogs]